A second new nuclear reactor is completed in Georgia. The carbon
ATLANTA (AP) — The second of two new nuclear reactors in Georgia has entered commercial operation, capping a project that cost billions more and took years longer than originally projected.
Georgia Power Co. and fellow owners announced the milestone Monday for Plant Vogtle’s Unit 4, which joins an earlier new reactor southeast of Augusta in splitting atoms to make carbon-free electricity.
Unit 3 began commercial operation last summer, joining two older reactors that have stood on the site for decades. They’re the first two nuclear reactors built in the United States in decades.
The new Vogtle reactors are currently projected to cost Georgia Power and three other owners $31 billion, according to calculations by The Associated Press. Add in $3.7 billion that original contractor Westinghouse paid Vogtle owners to walk away from construction, and the total nears $35 billion.
Related articles
NBA playoffs: Edwards leads Wolves to 98
DENVER (AP) — Anthony Edwards overcame a slow start and the Timberwolves roared back from a 20-point2024-05-21Pennsylvania Senate approves GOP's $3B tax
HARRISBURG, Pa. (AP) — Republican lawmakers on Tuesday advanced legislation for a $3 billion tax cut2024-05-21Scientists discover remains of a 'buried planet' deep inside EARTH
A new study of metal ore deep inside the moon is offering fresh evidence that Earth's natural satell2024-05-21Senators hire Travis Green as coach. Green leaves the Devils after serving in an interim role
OTTAWA, Ontario (AP) — The Ottawa Senators have hired Travis Green as coach, signing him to a four-y2024-05-21Socialite Jasmine Hartin enjoys beach snuggle with electrician hunk
Socialite Jasmine Hartin has been seen enjoying a beach snuggle with her new mystery man.Ms Hartin w2024-05-21Electricity from clean sources reaches 30% of global total
Billions of people are using different kinds of energy each day and 2023 was a record-breaking year2024-05-21
atest comment